Project Details

  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School
  • Avon Grove High School

Avon Grove High School

Remcon was awarded the site work package for this new 60-acre High School complex.

The site includes a new 350,000SF High School building, maintenance building, football stadium, (4) soccer fields, baseball field, softball field and tennis courts. The site also includes 6 sediment basins during construction that will be converted into 4 permanent basins. To maximize use of real estate onsite, there is also 6 underground infiltration basins totaling approximately 1,000,000 CF of storm water storage.

Project: New Avon Grove High School
Client: Lobar, Inc.
Location: West Grove, PA
Architect: KCBA Architects
Civil Engineer: Terraform Engineering, LLC.
Project Start: June 2020
Duration: Active

Remcon’s Scope of Work:

  • E&S Controls
  • Site Clearing and grubbing
  • 100,000CY of topsoil strip
  • 180,000CY of cut and fill
  • 30,000CY of structural fill import
  • 43,000SY of cement stabilization
  • 2 temporary storm water basins
  • 4 permanent storm water basins
  • 6 underground infiltration basins - Combined, these 6 basins consist of 9,220LF of pipe, 1,071 Storm Tech pieces, (27) concrete structures, (4) Nyloplast basins and 50,000TN+ of stone.
  • 12,260LF of storm water
  • 2,840LF of gravity sanitary sewer
  • 2,420LF of force main sanitary sewer
  • 4,940LF of waterline
  • 1,000LF of gas trench excavation and backfill
  • 13,560LF of excavation and backfill for concrete curb
  • 73,540SY of pavement subbase
  • 2,155SY of grass paver path subbase